top of page

CONSTRUCTION  UPDATES

  • 9-14-2023:  The new water mains are in service from Drexmore to Griffing and new service connections from Buckeye to Griffing on the west side are nearly complete. The re-aligned Ashwood Rd. intersection is in progress, and new curb has been installed on the east side from Griffing to Buckeye. Crews are continuing work to repair the pavement base and replacing curb and drive aprons as needed. This work will continue over the next two weeks.

​

  • 8-28-2023:  Water quality testing is completed and the new water mains are in service from Drexmore to Griffing. Work to install new service connections is in progress and will continue over the next two weeks. The re-aligned Livingston Rd. intersection is constructed and the old roadway pavement is being removed. Work to re-align the Ashwood Rd. intersection and to replace curb along the corridor will continue over the next two weeks.

​

  • 8-14-2023:  Water main installation is complete from Griffing Ave. to the Square. Tie-in of the new water main at the Square is under way. Once water quality testing is complete, crews will tie in the service lateral connections from the Square to Griffing, which is expected to continue over the next two weeks. Catch basin replacements, curb replacements, and pavement repairs are in progress and will continue. Construction of the Livingstone Rd. intersection re-alignment is in progress, to be followed by the re-alignment at Ashwood Rd.

​

  • 7-31-2023:  Crews have completed the installation of new water main on the southbound side of South Moreland, from Drexmore to Griffing. Work continuing into the next two weeks will include making lateral connections to the new water main and installing the underground conduits and new pole foundations between Drexmore and Griffing. 

​

  • 7-17-2023:  Crews have completed installation of water main and connections from Griffing to Drexmore on the northbound side of South Moreland. They are currently installing water main on the southbound side from Drexmore to Buckeye. Over the next two weeks they will continue the water main installation and make lateral connections from Buckeye to Griffing.

PAST PROJECT UPDATES

  • June 12, 2023 - The City of Cleveland will begin Stage 1 and Phase 1 of construction. Click the PDF link below to view the South Moreland, Shaker Square, North Moreland Improvements Traffic Advisory.

​

​

​

​

  • On March 15, 2023 the City of Cleveland hosted the Construction Phase Public Meeting.  The meeting was held at 6:30 PM at Greenview Campus of Positive Education (formerly known as Ludlow School). Construction is scheduled to begin in April of 2023 and this meeting provided information about construction activities along the corridor. Click the PDF link below to view the presentation provided at the meeting:

​​

​

​

​

​

  • January 3, 2023 - The City of Cleveland is currently evaluating  bids received by contractors in order to award the construction project. As more information becomes available it will be posted on this section of the website.  The website will also be used during construction for updated regarding maintenance of traffic and other pertinent construction activity notifications.  

​

  • On November 9, 2022, the City of Cleveland hosted Design Phase - Public Meeting #3 regarding the construction of the improvements along South Moreland Boulevard, Shaker Square and North Moreland Boulevard. See the Public Feedback page for the information presented and response to public comments. 

​

  • On September 30, 2022 Councilmember Gray hosted a project walk-through for interested members of the community to learn more about the proposed improvements along the corridor. 

​

  • On September 20, 2022, the City of Cleveland hosted Design Phase - Public Meeting #2 regarding the construction of the improvements along South Moreland Boulevard, Shaker Square and North Moreland Boulevard. See the Public Feedback page for the information presented and response to public comments.
     

  • On August 15, 2022, the City of Cleveland hosted Design Phase - Public Meeting #1 regarding the construction of the improvements along South Moreland Boulevard, Shaker Square and North Moreland Boulevard. See the Public Feedback page for the information presented, comments, and responses to comments.

bottom of page